28. (1) Where a development to which a certificate relates was substantially commenced or at a more advanced stage of completion on the dissolution day, but was not completed on that date, an application may be made to the Council for permission under section 34 of the Act of 2000 for so much of the development as was not completed on that date.
|
| |
(2) Where a permission is granted under section 34 of the Act of 2000 in respect of a development in relation to which an application was made under subsection (1), without prejudice to anything validly done in accordance with the certificate concerned prior to the grant of permission, that grant of permission shall have effect, and the certificate shall cease to have effect, in respect of so much of the development as was not completed on the dissolution day.
|