Minerals Development Act 2017
Extinguishment of right to compensation under section 122 | ||
124. (1) A person’s right to compensation under this Chapter is extinguished if the claim for compensation is not submitted to the Mining Board within 12 months, or such longer period allowed under subsection (2), after the first publication in Iris Oifigiúil of the notice referred to in section 123 (b) or, if the notice was delivered to the person under section 123 (c), after the date that the notice was delivered. | ||
(2) The Minister may, on the written application of a claimant, extend the period referred to in subsection (1) if the Minister is satisfied that good reasons exist for the failure of the claimant to submit a claim for compensation within the initial 12 month period, but any such extension shall not result in the period being extended to more than 24 months after the first publication in Iris Oifigiúil of the notice, or the date that the notice was delivered, as the case may be. |