Phasing plans
|
| |
178. (1) Where an application for permission under this Part relates to a proposed residential development consisting of not fewer than 10 housing units, the application for permission shall—
|
| |
(a) specify the duration of permission sought, and
|
| |
(b) be accompanied by a phasing plan.
|
| |
(2) A phasing plan referred to in subsection (1) shall specify—
|
| |
(a) the sequencing of the proposed development,
|
| |
(b) the schedule of works for the proposed development,
|
| |
(c) the periods within which specified phases of the proposed development are required to be completed, and
|
| |
(d) such further information as may be prescribed.
|
| |
(3) Where an application is required to be accompanied by a phasing plan, the planning authority or the Commission may attach as a condition to any grant of permission a requirement that the development comply with any specified provision of the phasing plan.
|
| |
(4) A condition under subsection (3) shall provide that any sequence or period specified in the phasing plan may be amended with the prior written agreement of the planning authority.
|
| |
(5) In this section “phasing plan” means a plan—
|
| |
(a) submitted by an applicant under this Part for residential development consisting of not fewer than 10 housing units,
|
| |
(b) that describes the intended sequencing and scheduling of the construction and commissioning activities of the development, and
|
| |
(c) that contains such other information as may be prescribed.
|