340. (1) If, within 8 weeks from the date of the coming into force of a notice under section 339 , or such longer period as may be agreed by the planning authority and the person to whom the notice is addressed, any measure specified in a notice under paragraph (c) of subsection (2) of section 339 has not been carried out to the satisfaction of the planning authority, the planning authority, or a person lawfully authorised by a planning authority to do so, may, subject to section 394 and subsection (2), enter the structure or land for the purpose of the measure. | ||
(2) A person entering land under subsection (1) shall ensure that— | ||
(a) reasonable steps are taken to minimise the disruption caused by such entry to any occupier of the land, and | ||
(b) such entry is effected at a reasonable time having regard to the use of the land or structure. |