SCHEDULE 10
Insertion of Eighth Schedule of Act of 2000
|
| |
Section 172
|
| |
“EIGHTH SCHEDULE
|
| |
Section 285
|
| |
Classes of Development specified for purposes of Chapter III of Part XXI
|
| |
1. Development referred to in the Seventh Schedule.
|
| |
2. Development consisting of a trading port or pier for loading and unloading goods that—
|
| |
(a) is connected to land, and
|
| |
(b) can accommodate vessels of over 1,350 tonnes.
|
| |
3. Development consisting of a pipeline that is not less than 20 kilometres in length and that is intended for the transport of—
|
| |
(a) gas, oil or chemicals, or
|
| |
(b) carbon dioxide (CO2) streams for the purposes of geological storage, including associated booster stations.
|
| |
4. Development consisting of the construction of an electrical power line that has a voltage of not less than 220 kilovolts and a length of not less than 15 kilometres.
|
| |
5. Development consisting of the laying of a telecommunications cable or pipeline of not less than 15 kilometres in length.
|
| |
6. Development consisting of the construction of a storage site within the meaning of Directive 2009/31/EC of the European Parliament and of the Council of 23 April 200925
on the geological storage of carbon dioxide and amending Council Directive 85/337/EEC, European Parliament and Council Directives 2000/60/EC, 2001/80/EC, 2004/35/EC, 2006/12/EC, 2008/1/EC and Regulation (EC) No 1013/2006.
|
| |
7. Development consisting of an installation for the capture of CO2 streams within the meaning of Directive 2009/31/EC of the European Parliament and of the Council of 23 April 2009—
|
| |
(a) intended for geological storage of CO2 within such meaning, or
|
| |
(b) where the intended capture of CO2 is not less than 1,500,000 tonnes per annum.
|
| |
8. Development consisting of the drainage or reclamation of not less than 2 hectares of wetland.
|
| |
9. Development consisting of a seawater fish breeding installation with an intended output exceeding 100 tonnes per annum.
|
| |
10. Development consisting of the reclamation of not less than 10 hectares of land from the sea.
|
| |
11. Development consisting of—
|
| |
(a) the extraction of stone, gravel, sand or clay where the area of extraction would be greater than 5 hectares, or
|
| |
(b) the extraction of stone, gravel, sand or clay by marine dredging (other than maintenance dredging), where the area of extraction would be greater than 5 hectares.
|
| |
12. Development consisting of deep drilling (other than deep drilling for the purposes of investigating the stability of the soil, seabed or substrata beneath the soil or seabed) for—
|
| |
(a) geothermal purposes, or
|
| |
(b) the purpose of securing water supplies exceeding 2 million cubic metres per annum.
|
| |
13. Development consisting of the construction or operation of—
|
| |
(a) an installation for the manufacture of vegetable or animal oils or fats, where the capacity for processing raw materials would exceed 40 tonnes per day, or
|
| |
(b) any fish-meal or fish-oil factory.
|
| |
14. Development consisting of the construction or operation of a sea water marina where the number of berths exceeds 300.
|
| |
15. Development consisting, or for the purposes, of—
|
| |
(a) a terminal, building or installation ancillary to a natural gas storage facility (either above or below the surface of the water or seabed) the storage capacity of which would exceed 1mscm, or
|
| |
(b) a terminal, building or installation ancillary to a terminal that is used for the liquefaction of natural gas or the importation, offloading and re-gasification of liquefied natural gas, and ancillary services.
|
| |
16. Development consisting, or for the purposes, of an installation for the storage of—
|
| |
(a) natural gas, where the storage capacity would exceed 200 tonnes,
|
| |
(b) combustible gases, where the storage capacity would exceed 200 tonnes, or
|
| |
(c) oil or coal, where the storage capacity would exceed 100,000 tonnes.
|
| |
17. An installation for the production of hydroelectric energy—
|
| |
(a) that has an output of not less than 20 megawatts,
|
| |
(b) that would result in the new or extended area of water impounded being not less than 20 hectares, or
|
| |
(c) that would result in a 30 per cent change in the maximum, minimum or mean flows in the main river channel or tidal bay concerned.
|
| |
18. An installation for the production of energy by harnessing the power of the wind that has—
|
| |
(a) more than 5 turbines, or
|
| |
(b) a total output of more than 5 megawatts.
|
| |
19. Any floating or fixed installation (either temporary or permanent) for the production of energy by harnessing the power of the sun.
|
| |
20. An installation for the production of energy by harnessing wave or tidal power that has a total output greater than 5 generating units or 5 megawatts.
|
| |
21. A harbour or port installation, including—
|
| |
(a) loading or unloading areas,
|
| |
(b) vehicle queuing and parking areas,
|
| |
(c) ship repair areas,
|
| |
(d) areas for berthing or dry docking of ships, and
|
| |
(e) areas for the weighing, handling or transport of goods or the movement or transport of passengers (including customs or passport control facilities),
|
| |
and any associated offices or other similar facilities that would—
|
| |
(i) result in the enclosed area of water in the harbour or port installation being not less than 20 hectares,
|
| |
(ii) involve the reclamation of an area of land of not less than 5 hectares,
|
| |
(iii) involve the construction of a quay greater than 100 metres in length, or
|
| |
(iv) be capable of admitting a vessel of more than 1,350 tonnes.”.
|
| |
25 OJ No. L140, 5.6.2009, p.114 |