Planning authority’s power to carry out works to protected structures, proposed protected structures and structures in architectural conservation areas

323. Where a person on whom a planning authority has served a notice under section 312 , 313 or 314 , or where a court order is made under section 315 or 317 in respect of such a notice, fails to comply with the notice or order, the planning authority may take such steps as it considers reasonable and necessary to give effect to the terms of the notice or order, including—

(a) entry on land by authorised persons in accordance with section 394 , and

(b) the carrying out, or arranging the carrying out, by an authorised person of the works specified in the notice or order.